Science and Technology Center (Aerial)

Published Tuesday, February 25th, 2014

Science and Technology Center (Aerial) 01/2014

science and technonogySTC


The Penthouse and stair tower steel is nearing completion. In the upcoming weeks the tower crane will be removed from the job site and exterior masonry will begin. Interior masonry walls, telecom, fire alarm, electrical conduits, and HVAC (heating, ventilation, and air conditioning) ductwork are progressing on all levels. Exterior onsite telecom and electrical ductbanks are in the final stages. Mechanical rooftop units are in place, and temporary roofing to be installed in the upcoming weeks. Overall progress is tracking well, but with the winter weather ahead we are anticipating some impacts on the schedule.  Click here to return to homepage. 

As always, thank you for your cooperation and support as we continue to make progress at Coppin.