Science and Technology Center (STC)

Published Tuesday, November 12th, 2013

STC progress, aerial view

PROGRESSION!

The underground utility work for the connection to the Health and Human Services Building (HHSB) is going well. The pipes are in place in the boiler room and the physical penetration through the building is complete. The pipe installation will be continuous over the next several months as we move toward the final connections to the STC. Structural concrete is progressing. The third floor pour is now finished and the contractors have started setting up for the fourth floor pour. Visit our website for more news.

 


 

structural progressSTC, structure, construction, progressWork in progress


As always, thank you for your cooperation and support as we continue to make progress at Coppin.