STC Exterior/Interior Progress

Published Wednesday, February 12th, 2014

STC Exterior

The New Science and Technology Center (STC)

The structural concrete is complete and the tower crane removed. Interior masonry walls, telecom, fire alarm, electrical conduits, and HVAC (heating, ventilation, and air conditioning) are progressing on all levels. Mechanical and plumbing rough-ins are complete on the first floor and 80% complete on the second. Exterior onsite telecom and electrical ductbanks are in the final stages. Mechanical rooftop units and boilers are also in place. Overall progress is tracking well, but with the winter weather ahead, we are anticipating some impacts on the schedule.  Click here to return to homepage.

As always, thank you for your cooperation and support as we continue to make progress at Coppin.